Operations September 16, 2026

MRN begins implementation of R$ 5 billion project and advances transmission line in Pará

4th edition of Inside MRN highlights the implementation of new areas, the energy transition and the economic, social and environmental results of the first half of the year

Mineração Rio do Norte (MRN) has begun implementing the New Mines Project (PNM), which foresees R$ 5 billion in investments over five years and is expected to ensure the continuity of its operations in western Pará until 2041. At the same time, the company is advancing the construction of a transmission line that will connect its operation to the National Interconnected System. In the first half of the year, R$ 36.9 million were invested in community and environmental initiatives. These projects and results are the highlights of the 4th edition of “Inside MRN”, a half-yearly publication presenting the company's economic, social and environmental performance.

MRN professional in a green hard hat smiling in front of one of the company's locomotives

With the Installation License obtained in April this year, the PNM entered the implementation phase and is expected to create 2,300 new jobs during construction. The project expands opportunities for local professionals and suppliers in the development of new mining areas in Oriximiná, Terra Santa and Faro. “The New Mines Project connects production, employment, regional development and industrial competitiveness. The benefits begin in the territory, but their effects reach the entire aluminum chain and different sectors of the country's economy,” says MRN CEO Guido Germani.

To prepare local professionals for the opportunities associated with the project, the company offered 1,200 free places in 14 vocational courses in areas such as civil construction, machine operation, welding and maintenance. “Creating opportunities depends on training people and strengthening local capacity to meet the demands ahead,” says HR general manager Magda Damasceno. The first classes of the Workforce Management Program (PGMO) began training in the first half of July and, depending on the length of each course, may run until July 2027.

Transmission line reaches 63% completion

The second strategic project is the 230 kV transmission line that will connect MRN's operation to the National Interconnected System. The work reached 63% physical progress in June 2026 and completed the five towers for the Trombetas River crossing, considered one of the most complex stages of the project. With 98 kilometers and 232 towers, the line is scheduled to start operating in the first quarter of 2027. The change in the energy matrix is expected to reduce greenhouse gas emissions associated with power generation by 90%.

“We overcame technical, environmental and occupational challenges while fully meeting the project's license conditions. This result strengthens our confidence for the next stages of implementation,” says Yanto Araújo, MRN's general manager of Projects. Construction of the transmission line generated 1,100 jobs, 67% of which were filled by workers from Pará. The project also maintains dialogue with 19 communities in its area of direct influence and carries out actions to prevent risks associated with large projects.

Purchases in Pará total R$ 448 million

The publication also presents MRN's results for the first half of 2026. In the period, the company produced 5.5 million tonnes of bauxite and made R$ 470.2 million in investments. Purchases of materials and services in Pará totaled R$ 448.3 million, while taxes, fees and contributions paid exceeded R$ 200.1 million. The company maintained 7,711 workers. Among its direct employees, 85.61% are from Pará. To increase the participation of local companies in its supply chain, MRN held meetings with business associations and entrepreneurs in Santarém, Óbidos, Oriximiná, Faro and Terra Santa.

Social and environmental investment and community development

In the first half of the year, MRN invested R$ 12.9 million in social and environmental projects and actions for communities, with initiatives in education, health, safety, income generation and community strengthening. Another R$ 24 million went to environmental programs, notably the reforestation of 207.6 hectares and the planting of more than 280,000 seedlings of native species. The Boa Nova and Saracá communities supplied 1.9 tonnes of seeds to MRN's Forest Nursery, an initiative that combines environmental recovery, appreciation of traditional knowledge and income generation.

The full 4th edition of “Inside MRN” is available at the publication link. MRN in numbers, first half of 2026: 5.5 million tonnes of bauxite produced; R$ 470.2 million in investments; 7,700 workers, with 85.61% of direct employees from Pará; R$ 448.3 million in purchases in the state; R$ 200.1 million paid in taxes, fees and contributions; R$ 5 billion planned for the New Mines Project over the next five years; 2,300 jobs expected during implementation; 1,200 free places in 14 vocational courses; 63% physical progress on the Transmission Line Project; 1,100 jobs created in the line construction, 67% filled by people from Pará; R$ 12.9 million invested in social and environmental actions; 60 initiatives; 3,700 people benefited; R$ 24 million invested in environmental programs; 207.6 hectares reforested; 280,000 native seedlings planted; 1.9 tonnes of seeds purchased from local communities; 214 water monitoring points.