MRN completes first tower of the Trombetas River crossing and advances Transmission Line works

The 150-meter structure marks one of the most complex stages of the project, which will connect the operation to the National Interconnected System and reduce carbon emissions

One of the most complex infrastructure projects under way in western Pará has just reached a new milestone. Mineração Rio do Norte (MRN) has completed the assembly of the first tower of the Trombetas River crossing for the Transmission Line Project (PLT), which will connect the company to the National Interconnected System (SIN). At 150 meters tall, the structure was completed in compliance with the project's social and environmental license conditions. Along 5.2 kilometers over the river, five large towers will be installed, in one of the most challenging stages of the work. Assembling the structures at the crossing involves engineering, logistics, environmental and safety challenges typical of the Amazon. The work requires heavy equipment, specialized transport and detailed planning to operate in a hard-to-reach region. The next stages of the PLT include the assembly of the other four crossing towers, scheduled for June and July. Tower 28, currently under construction, will reach 178 meters in height.

Transmission towers at the Trombetas River crossing seen from above

For MRN Projects manager Yanto Araújo, completing the first tower consolidates work that demands a high degree of integration and planning. “This assembly required robust engineering, extensive mobilization of resources and coordination between teams and partner companies. We overcame technical, environmental and occupational challenges while fully meeting the project's license conditions. This strengthens our confidence for the next stages of the crossing.” Yanto adds that there were no recorded accidents.

Half of the structure is concentrated at the crossing

Sérgio Reis, manager of MRN's Construction Department, explains that this section accounts for about 50% of all the concrete, steel and metal structures planned for the PLT. According to Reis, this complexity also reflects the importance of the project: “Completing the first tower and advancing the second demonstrate the teams' technical capacity to carry out a project of this magnitude in the Amazon, with safety, planning and responsibility.”

PLT works include clearing the right-of-way, building foundations and assembling towers, as well as implementing substations. During construction, MRN adopts environmental control measures such as fauna and flora monitoring and rescue and the use of techniques to reduce impacts on aquatic species, rivers, lakes, streams, soil and forests. The company maintains dialogue with 19 communities in the area of influence through meetings, social and environmental assessments and actions to follow up on the stages of the work.

Completing the assembly of the first structure and advancing the second mark a challenging stage

Cleaner energy

The 98-kilometer transmission line in western Pará is a strategic MRN initiative to increase its energy efficiency. The project foresees connecting the unit to the National Interconnected System (SIN) through a 230 kV line that will link the Oriximiná substation to the future Saracá substation in Porto Trombetas. With the connection to the SIN, the company expects to reduce its carbon footprint by 25% from 2027.

The work boosts the regional economy by hiring workers, suppliers and services in the region. One year after implementation began, the PLT had generated 847 direct jobs, 460 of them filled by workers from Oriximiná, the municipality where the company's operation is located. The progress of the energy infrastructure runs in parallel with the New Mines Project (PNM), which is in the licensing phase and is considered strategic for the long-term continuity of MRN's operations.